Which pipes first, with a capital plan cut by a fifth?
Client
Regional water utility, 2.1 million customers
Engagement
Run it with you
Result
Leakage down 14%
When
11 months into the plan

The range
Forecast, decided, landed.
Before the work the outcome could have been anywhere in the wide band. At the decision the band was narrow enough to commit to. The line is what happened.
Forecast before the work
Forecast at the decision
Where it landed
% leakage
The situation
Why it was stuck.
The regulator cut the five-year capital allowance by 19%. The renewal list had been built for the full budget.
Engineering and finance each had a ranking of which mains to replace first; the two lists shared fewer than half their items.
The options
Dropped: Cut every programme by 19%
Simple, and the worst outcome on leakage.
Chosen: Rank by risk and leakage per dollar
Chosen. One list, agreed by both teams.
Dropped: Defer renewals, spend on pressure management
Kept for two zones only.
01 / What we did
Phase by phase.
Set up
One shared ranking model and six numbers for the weekly page.
Run together
Monthly capital reviews prepared with engineering and finance.
Hand over
The utility’s planning team runs the reviews; we read and challenge.
-14%
leakage, month 11
1
renewal list, from two
4 of 4
regulator milestones met
The monthly review stopped being a fight about whose list was right.
Director of asset management, regional water utility, 2.1 million customers