Manufacturing

·

United Kingdom

Buy a fourth line, or run three lines on a new shift pattern?

Client

Industrial bakery group, 3 plants

Engagement

Diagnostic

Result

Capacity +18% without a new line

When

6 months after the decision

A bakery operator in a white coat sorting loaves from a conveyor into crates

The range

Forecast, decided, landed.

Before the work the outcome could have been anywhere in the wide band. At the decision the band was narrow enough to commit to. The line is what happened.

Forecast before the work

Forecast at the decision

Where it landed

% capacity

0%+17%+34%Before: +2% to +30%At decision: +14% to +21%Landed +18%, month 6DecisionMonth 6

The situation

Why it was stuck.

Two supermarket contracts needed 15% more output within a year. The plant team had a quote for a fourth production line at $7.4 million.

Changeovers between products took between 40 and 95 minutes, depending on the shift.

The options

Dropped: Fourth production line

Twenty months to install; did not meet the contract dates.

Chosen: New shift pattern and changeover standard

Chosen. Met both contracts inside six months.

Dropped: Outsource two product lines

Margin loss larger than the line cost over five years.

01 / What we did

Phase by phase.

Map

Line data for 26 weeks and time on the floor across all shifts.

Test

A changeover standard trialled on one line for two weeks.

Decide

Read-out with the plant directors; the line purchase was paused.

+18%

output on the same three lines

38 min

average changeover, from 64

$7.4M

capital not spent

We were about to buy a line to fix a scheduling problem.

Group operations director, industrial bakery group, 3 plants

Team

Mara Brandt, founding partner · Dev Raman, partner

Tell us the decision you keep putting off.

A partner replies within one working day.

Book a 30-minute call →