Buy a fourth line, or run three lines on a new shift pattern?
Client
Industrial bakery group, 3 plants
Engagement
Diagnostic
Result
Capacity +18% without a new line
When
6 months after the decision

The range
Forecast, decided, landed.
Before the work the outcome could have been anywhere in the wide band. At the decision the band was narrow enough to commit to. The line is what happened.
Forecast before the work
Forecast at the decision
Where it landed
% capacity
The situation
Why it was stuck.
Two supermarket contracts needed 15% more output within a year. The plant team had a quote for a fourth production line at $7.4 million.
Changeovers between products took between 40 and 95 minutes, depending on the shift.
The options
Dropped: Fourth production line
Twenty months to install; did not meet the contract dates.
Chosen: New shift pattern and changeover standard
Chosen. Met both contracts inside six months.
Dropped: Outsource two product lines
Margin loss larger than the line cost over five years.
01 / What we did
Phase by phase.
Map
Line data for 26 weeks and time on the floor across all shifts.
Test
A changeover standard trialled on one line for two weeks.
Decide
Read-out with the plant directors; the line purchase was paused.
+18%
output on the same three lines
38 min
average changeover, from 64
$7.4M
capital not spent
We were about to buy a line to fix a scheduling problem.
Group operations director, industrial bakery group, 3 plants
Team
Mara Brandt, founding partner · Dev Raman, partner